To end 2015 on a positive note, Peter Hillreiner has successfully tendered for a new 2750m2 factory unit at the existing Starglaze window manufacturing facility at Waterside South near Lincoln City Centre.

This contract renews our partnership with RG Carter whom we successfully delivered together Stamford Sports College in 2014. This contract is being managed by RG Carter Lincoln office where we have had the opportunity to meet their key individuals who have expressed their desire to work with us in the future. We assume that this wish has been fuelled by the location of RG Carter’s office which is approximately 200 metres from our recent and ongoing efforts for Hobson & Porter on phase 1 (completed) & phase 2 (ongoing) on the new agricultural complex at the Lincolnshire show ground.

Adam Turner is presently on site and nearing completion of 600mm deep pile mat in readiness for the pillars in the New Year.  Work is expected to continue into autumn 2016.